Construction of the first converter at the Leingarten substation near Heilbronn by TransnetBW began in July 2023. The official start of construction of the first northern section of the "ElbX" line in Wewelsfleth (Schleswig-Holstein) was 11 September 2023: In the first construction section, which is considered technically challenging and is around 5.2 km long, an accessible tunnel with an internal diameter of 4 m is to be built under the Elbe.
Commissioning of the power line, which is intended to secure the supply of wind power (onshore and offshore) to Bavaria and Baden-Württemberg, is planned for 2028. As the line is designed for direct current, it can only go into operation as a whole and not in sections.
b) SuedOstLink: Backup power for Isar 2 nuclear power plant
SuedOstLink, which will realise two underground direct current connections (2 GW each) at the
525 kV voltage level, runs for around 540 km between Wolmirstedt near Magdeburg (Saxony-Anhalt) to the Isar site near Landshut (Bavaria).
The project developer is 50Hertz, which is responsible for the northern section of the electricity motorway. The southern part of the route, located in Bavaria, is the responsibility of the transmission system operator and project developer TenneT. Construction of the converter at the Wolmirstedt site (Magdeburg) began in March 2023.
The southern part of the route, which is located in Bavaria, is in turn the responsibility of the transmission system operator and project developer TenneT.
On 11 December 2023, even before the planning approval decision was made, the start of construction work for the converter at the Isar site near Landshut was celebrated in the presence of Bavaria's Minister President Dr. Markus Söder and Minister of State Hubert Aiwanger.